Q1. What are the phases of a Project Development Cycle? Give the salient tasks under each phase.

Q2. What are the traditional methods of financial evaluation of the projects? Give a comparative analysis of these methods.

Q3. Discuss the usefulness of matrix organization in project management. Also explain the recent trend in organization design.

Q4. Elaborate the concept of Earned Value of the Budget in PERT/COST System.

Q5. Explain the concept of CYBERNETICS applied to project management.

Q6. The following information is given for a project

Activity : A B C D E F G

Immediate Predecessor : - A A C B,D D E,F

Time (Weeks) : 6 3 7 2 4 3 7

a) Draw the network

b) Identify Critical Path

c) Calculate the project completion time

d) Calculate the Float of each activity